New leaking tank troubling for Hanford

SPOKANE, Wash. (AP) - A large, double-walled tank of waste at the nation's most contaminated nuclear site is leaking into its outer shell, raising new concerns about the long-term storage of the radioactive brew and for the effects on the environment if the waste escapes.
The nation's largest collection of deadly wastes left behind from the production of nuclear weapons sits at south-central Washington's Hanford nuclear reservation. Late last month, the U.S. Department of Energy, which oversees the site, revealed a slow leak in the oldest of 28 double-shell waste tanks, AY-102, saying a small amount of waste was leaking into the space between the inner and outer walls.
No waste is believed to have leaked into the environment on the reservation near Richland, the agency said.
That was little comfort to state officials already bemoaning the federal government's long-stalled efforts to build a massive plant to treat the waste.
"The results of the Department of Energy's investigation are concerning," said Washington Gov. Chris Gregoire, who has long pushed for Hanford cleanup. "Already, waste has been sitting in these double-shelled tanks past the tanks' life expectancy."
The sprawling Hanford site was built as part of the top-secret Manhattan Project in World War II to make plutonium for nuclear weapons. The leftovers - some 53 million gallons of a radioactive, toxic stew - were first stored in 177 underground single-walled tanks. Many of those tanks have leaked, threatening the nearby Columbia River.
Starting in the 1970s, the government built 28 double-walled tanks to store the most dangerous of the waste until it could be treated for permanent disposal.
That day is still a long way off.
The plant under construction to convert the waste into a stable glass form has suffered skyrocketing costs, technical problems and construction delays for years. Long considered the cornerstone of Hanford cleanup, design of the plant is 85 percent complete and construction is half done,
Most recently, the plant had been scheduled to begin operating in 2019, but the Energy Department pushed off for at least a year a new estimate on the plant's start date and cost while it embarks on additional tests to resolve technical problems with its design and construction.
The last cost estimate: $12.3 billion.
In addition, plans for permanently storing that waste once it's treated are still unresolved, since the federal government halted development of the Yucca Mountain nuclear storage site in Nevada.
The state Department of Ecology is working with federal officials to decide how to deal with the leak. The leaking tank is just past its design life of 40 years, but state officials still expected it to last much longer than that, according to Ecology spokesman Dieter Bohrmann.
A plan on what to do next is expected soon, he said.
The Energy Department said Tank AY-102 went into service in 1971 and is the oldest of the double-walled tanks. It has a capacity of 1 million gallons and currently holds 707,000 gallons of liquid wastes and 151,000 gallons of sludge.
By comparison, an Olympic-sized swimming pool holds 660,000 gallons of water.
The state also is worried about the integrity of the remaining 27 double-walled tanks, Bohrmann said, especially the leaker's companion tank known as AY-101.
"The thought was always that these double-shell tanks were stable," he said, adding that the new leak "complicates the tank waste retrieval and cleanup mission."
The Energy Department says workers first spotted material at several locations in the 30-inch area between the walls during routine monitoring in August. It took until October to confirm it was radioactive waste. The agency says there is no evidence the leak is growing or that it has escaped where it was detected.
For now, plans call for twice-weekly visual inspections using remote cameras, and regular checks of liquid levels inside the primary tank, said Tom Fletcher, assistant manager for Hanford's tank farms.
Routine monitoring has not detected leaks in any of the other double-shell tanks. Expanded inspections are planned on six of those with similar construction and storage history.
A Hanford watchdog said the leak was entirely predictable, and that the government should never have reached this crisis stage.
State Rep. Gerald Pollet, D-Seattle, a long-time advocate for Hanford cleanup, plans to seek a legislative hearing on why the state of Washington has not long demanded a contingency plan.
The state should have insisted that the Energy Department construct newer storage tanks as delays have mounted with plant construction, Pollet said.
"It's a huge setback for cleanup efforts and requires a Plan B that should have been in place years ago," Pollet said. "It's not like anyone thought the double-shell tanks wouldn't leak."
The nation's largest collection of deadly wastes left behind from the production of nuclear weapons sits at south-central Washington's Hanford nuclear reservation. Late last month, the U.S. Department of Energy, which oversees the site, revealed a slow leak in the oldest of 28 double-shell waste tanks, AY-102, saying a small amount of waste was leaking into the space between the inner and outer walls.
No waste is believed to have leaked into the environment on the reservation near Richland, the agency said.
That was little comfort to state officials already bemoaning the federal government's long-stalled efforts to build a massive plant to treat the waste.
"The results of the Department of Energy's investigation are concerning," said Washington Gov. Chris Gregoire, who has long pushed for Hanford cleanup. "Already, waste has been sitting in these double-shelled tanks past the tanks' life expectancy."
The sprawling Hanford site was built as part of the top-secret Manhattan Project in World War II to make plutonium for nuclear weapons. The leftovers - some 53 million gallons of a radioactive, toxic stew - were first stored in 177 underground single-walled tanks. Many of those tanks have leaked, threatening the nearby Columbia River.
Starting in the 1970s, the government built 28 double-walled tanks to store the most dangerous of the waste until it could be treated for permanent disposal.
That day is still a long way off.
The plant under construction to convert the waste into a stable glass form has suffered skyrocketing costs, technical problems and construction delays for years. Long considered the cornerstone of Hanford cleanup, design of the plant is 85 percent complete and construction is half done,
Most recently, the plant had been scheduled to begin operating in 2019, but the Energy Department pushed off for at least a year a new estimate on the plant's start date and cost while it embarks on additional tests to resolve technical problems with its design and construction.
The last cost estimate: $12.3 billion.
In addition, plans for permanently storing that waste once it's treated are still unresolved, since the federal government halted development of the Yucca Mountain nuclear storage site in Nevada.
The state Department of Ecology is working with federal officials to decide how to deal with the leak. The leaking tank is just past its design life of 40 years, but state officials still expected it to last much longer than that, according to Ecology spokesman Dieter Bohrmann.
A plan on what to do next is expected soon, he said.
The Energy Department said Tank AY-102 went into service in 1971 and is the oldest of the double-walled tanks. It has a capacity of 1 million gallons and currently holds 707,000 gallons of liquid wastes and 151,000 gallons of sludge.
By comparison, an Olympic-sized swimming pool holds 660,000 gallons of water.
The state also is worried about the integrity of the remaining 27 double-walled tanks, Bohrmann said, especially the leaker's companion tank known as AY-101.
"The thought was always that these double-shell tanks were stable," he said, adding that the new leak "complicates the tank waste retrieval and cleanup mission."
The Energy Department says workers first spotted material at several locations in the 30-inch area between the walls during routine monitoring in August. It took until October to confirm it was radioactive waste. The agency says there is no evidence the leak is growing or that it has escaped where it was detected.
For now, plans call for twice-weekly visual inspections using remote cameras, and regular checks of liquid levels inside the primary tank, said Tom Fletcher, assistant manager for Hanford's tank farms.
Routine monitoring has not detected leaks in any of the other double-shell tanks. Expanded inspections are planned on six of those with similar construction and storage history.
A Hanford watchdog said the leak was entirely predictable, and that the government should never have reached this crisis stage.
State Rep. Gerald Pollet, D-Seattle, a long-time advocate for Hanford cleanup, plans to seek a legislative hearing on why the state of Washington has not long demanded a contingency plan.
The state should have insisted that the Energy Department construct newer storage tanks as delays have mounted with plant construction, Pollet said.
"It's a huge setback for cleanup efforts and requires a Plan B that should have been in place years ago," Pollet said. "It's not like anyone thought the double-shell tanks wouldn't leak."
This is an old story.  Five years ago a relative of mine in New Zealand, invented a gel to safely store nuclear waste underground. Why we do not have access to this or common knowledge of this astounds me.
At least we are no longer dumping this in the ocean. The Soviets did with their decommissioned nuclear reactors and radioactive waste, massive amounts of which are now sitting at the bottom of the Kara Sea in the Arctic Ocean. To wit, some 17,000 containers of radioactive waste, 19 ships with radioactive waste, 14 decommissioned nuclear reactors, a nuclear submarine, and a host of other nefarious materials. If any of these explode under water the consequences would be unspeakable.  Now the Soviets want to clean this up and look for oil. Not a chance. This will cause a major disturbance in the ocean surface. Expect many problems in the future.  This is a WORLD issue, not just Hanford.Â
So they can launch that little Air Force spacecraft that replaced the shuttle from Washington, and recover it IN Washington. They can already do that. I wonder why they don't, and it wouldn't surprise me if they did, load up trucks from Hanford and drive them across central BF Washington somewhere to launch small amounts of it at a time and just huck it into space. NASA missions were televised. These are controlled by the Air Force and are subject to secrecy. They don't even have to tell us that they're launching them.
Â
That's crackpot thinking, of course. Actually, they're using it to power HAARP and manipulate the weather. Isn't it weird that this started happening right before the election?
Just put it into a larger tank...then when that leaks put it into a even larger tank...repeat as needed
Â
HANFORD! man almighty, if it does breach its shell it will not be pretty, bye, bye to anything around or near it. Just think of what would happen when we get a nice big earth quake, to both Handford and WOOPS! You 2 were the biggest WOOPS ever made!
 @lee986321 Woops (WPPSS {Washington Public Power Supply System}) is completely harmless. It looks big and intimidating, but no fuel or anything else radioactive was ever transported up the mountain anywhere near the Satsop site. :P
 @lee986321 Even the rabbits they test are 'glowing' along with the fox's and raptors that eat them. Too late if one follows the latest news about fish that have been tested from Hood River down to Astoria and that did not include Willapa Bay...Â
http://www.youtube.com/watch?v=jjFjb285cRU
This facility is such as giant mess from the top to bottom. Â They also have a few football field sized pits where they are dumping low level contaminated soil every day!
This is like the relatives that won't move out - it just keeps costing more and more and more. And the gov't keeps the same people on that are supposed to be "safing" the place. They must have the gubment by the nads to keep getting the contract?
I say ship it to China, they are buying everything else that are our problems.